6 Milestones Completed
40 Participants Trained
24 Institutions Engaged
15 mo Project Duration

Milestones

Deliverables

Four key deliverable areas tracking overall project progress

Completed

1. Curriculum Development

Initial survey, curriculum design, and prototyping platform for locally-hosted LLM training materials.

Key Indicators

  • At least 8 survey responses from IDREN institutions
  • 1 draft curriculum developed
  • 1 demo prototype shared for feedback

Activities

Activity Target Status
Initial Needs Assessment Survey
Conducted as part of project kickoff (Jan 2026)
1 report Completed
Curriculum Design and Development
Finalized from pilot feedback; delivered as the two-day, nine-session workshop program
1 curriculum Completed
Module Development (5 modules)
Participant preparation and Sessions 2–6 materials published under an open license — see materials
5 modules Completed
Platform Prototyping
Demo platform used at pilot test, Sep 25, 2026
1 prototype Completed
Pilot Feedback Collection
Evaluation survey completed at pilot test, Sep 25, 2026 — see report
1 report Completed
Developing a Webpage Portal
llmnetops.github.io live with project news, workshop materials, and media coverage; updated continuously
1 website Completed
In Progress

2. Workshop Delivery

Two hands-on workshop sessions focusing on LLM fundamentals and AI agentic workflows for network operations.

Key Indicators

  • 2 workshop sessions delivered
  • 20+ participants trained
  • 70% knowledge improvement demonstrated

Activities

Activity Target Status
Workshop Planning
Pilot test Sep 25, 2026; registration Oct 6–31, 2026; participants confirmed by email
Complete planning Completed
Workshop Session 1: LLM Fundamentals
Day 1 — Nov 6, 2026, Ijen Suites Malang (Sessions 1–4); 40 participants from 24 institutions
1 session Completed
Workshop Session 2: AI Agentic Workflow
Day 2 — Nov 7, 2026, Ijen Suites Malang (Sessions 5–9) — see report
1 session Completed
Workshop Documentary
Day 1 and Day 2 photos in the Photo Gallery, workshop report, and 7 media articles published
Complete documentation In Progress
Not Started

3. Survey and Analysis

Comprehensive survey, case studies, and whitepaper development to document project impact.

Key Indicators

  • Final survey completed
  • 3+ case studies documented
  • 1 whitepaper published

Activities

Activity Target Status
Final Survey & Data Collection 1 survey report Not Started
Case Brief & Testimonial Collection 3+ case studies Not Started
Whitepaper on NetOps with AI 1 whitepaper Not Started
Not Started

4. Reporting

Project reporting and dissemination of findings to stakeholders and funding organization.

Key Indicators

  • Midterm report submitted
  • Final report completed
  • Findings disseminated

Activities

Activity Target Status
Midterm Reporting 1 midterm report Not Started
Final Report Writing & Dissemination 1 final report Not Started